14 November 2024
16 November 2024
19 November 2024
6 November 2024
23 October 2024
21 October 2024
24 September 2024
8 October 2024
5 October 2024
25 September 2024
24 September 2024
23 September 2024
24 September 2024
21 September 2024
23 September 2024
21 September 2024
7 September 2024
7 September 2024
3 August 2024
2 September 2024
31 August 2024
23 August 2024
22 August 2024
17 January 2023
13 August 2024
10 August 2024
8 August 2024
7 August 2024
8 August 2024
27 July 2024
3 August 2024
8 July 2024
Wednesday 11 May 2022 | Written by Caleb Fotheringham | Published in Economy, National
Batty said the stream bed alignment, stream bank rebuild, handrails, footpath ramps, rebuild of the vaka shed and paving of the road with asphalt were yet to be completed.
The ropes which act as speed bumps will be removed when the asphalt road has been completed, which is expected to take another two months.
Work on the Empire Bridge replacement began on August 11 last year.
The project was divided into five stages, the first was the temporary support system to the original bridge and the second was the temporary bypass bridge. Stages three to five of the project, were the removal and replacement of the existing bridge and stream works.
Construction of the new bridge cost $5 million.